JURMATEKS : Jurnal Manajemen Teknologi & Teknik Sipil e ISSN2621-7686 Volume 4 Nomor 2 Tahun 2021 Optimalisasi Biaya dan Waktu Proyek Kontruksi Pelebaran Jalan Menggunakan Earned Value http://dx.doi.org/ 10.30737/jurmateks © 2021 JURMATEKS. Jurnal Manajemen & Teknik Sipil. All rights reserved. Optimalisasi Biaya dan Waktu Proyek Kontruksi Pelebaran Jalan Menggunakan Earned Value S. T. Wibowo 1* , Suwarno 2 , A. Ridwan 3 , H. Wicaksono 4 , F. Rahmawaty 5 1*,2,3 Fakultas Teknik, Universitas Kadiri. Email: 1* sentottriwibowo@gmail.com A R T I C L E I N FO A B S T R A C T Article history : Artikel masuk : 06 06 2021 Artikel revisi : 27 08 2021 Artikel diterima : 03 09 2021 In a construction project, there are several aspects that cause the project not to go according to plan. Cost and time are aspects that need to be considered to avoid losses incurred in a project. Jombang-ploso-legundi-gresik road project is one of the road widening projects carried out by PT. Mix Pro Indonesia. The project was carried out with the aim that access to (Surabaya-Mojokerto) or further trans Java toll road is quicker safe and smoother. This research aims to optimize the cost and time on the project using the Earned Value method. Calculations include the calculation of ACWP (Actual Cost of Work Performance), BCWS (Budgeted Cost Work Schedule), and BCWP (Budgeted Cost for Work Performed) using the Earned Value method. From these parameters, estimate aspects of cost and time. As well as project analysis of acceleration on a critical trajectory of work. The results of calculations in the 12th week obtained a BCWS value of Rp 1,216,677,846,400 BCWP = Rp 3,040,372,140,080, ACWP = Rp 3,678,560,000. CV value = -Rp 109,203,495.92, SV = Rp 895,646,816.82, CPI = 0.827, and for SPI = 2,499. From these results it can be seen that the CPI value < 1 which means that there are project expenditures that exceed the original plan. With the results, it can be used as a reference in the implementation of project activities. Keywords : Earned Value, Project Delay, Project Management, Road Construction Style IEEE dalam mensitasi artikel ini: [1] B. Damara and R. Hepiyanto, “Optimalisasi Waktu dan Biaya Pada Proyek Gedung Pertanahan Nasional Kota Blitar Dengan Metode Critical Path Method (CPM),” J. Manaj. Teknol. Tek. Sipil, vol. 4, no. 1, pp. 119133, 2021, doi: 10.1016/j.jksues.2019.09.005. 1. Pendahuluan Proyek konstruksi jalan merupakan salah satu proyek yang telah berkembang cukup pesat. Jalan menjadi salah satu sarana transportasi yang berpengaruh terhadap kegiatan masyarakat. Pembangunan jalan menunjang perkembangan suatu wilayah serta peningkatan perekonomian. Dengan adanya jalan, mobilitas dalam segala hal menjadi lebih mudah sehingga akan memberikan dorongan ekonomi yang lebih kuat. Meningkatnya jumlah kendaraan serta pengguna jalan, harus diimbangi dengan pemeliharaan jalan seperti perbaikan konstruksi hingga pelebaran jalan. Proyek pelebaran jalan Jombang-Ploso-Legundi-Gresik menjadi salah satu proyek pembangunan jalan yang dikerjakan di ruas Provinsi jatim. Proyek Tersedia Secara Online di http://ojs.unik-kediri.ac.id/index.php/jurmateks/index http://dx.doi.org/ 10.30737/jurmateks JURMATEKS