Optimalisasi Biaya dan Waktu Proyek Kontruksi Pelebaran Jalan Menggunakan Earned Value
http://dx.doi.org/ 10.30737/jurmateks
© 2021 JURMATEKS. Jurnal Manajemen & Teknik Sipil. All rights reserved.
Optimalisasi Biaya dan Waktu Proyek Kontruksi Pelebaran Jalan
Menggunakan Earned Value
S. T. Wibowo
1*
, Suwarno
2
, A. Ridwan
3
, H. Wicaksono
4
, F. Rahmawaty
5
1*,2,3
Fakultas Teknik, Universitas Kadiri.
Email:
1*
sentottriwibowo@gmail.com
A R T I C L E I N FO A B S T R A C T
Article history :
Artikel masuk : 06 – 06 – 2021
Artikel revisi : 27 – 08 – 2021
Artikel diterima : 03 – 09 – 2021
In a construction project, there are several aspects that cause
the project not to go according to plan. Cost and time are
aspects that need to be considered to avoid losses incurred in a
project. Jombang-ploso-legundi-gresik road project is one of
the road widening projects carried out by PT. Mix Pro
Indonesia. The project was carried out with the aim that access
to (Surabaya-Mojokerto) or further trans Java toll road is
quicker safe and smoother. This research aims to optimize the
cost and time on the project using the Earned Value method.
Calculations include the calculation of ACWP (Actual Cost of
Work Performance), BCWS (Budgeted Cost Work Schedule),
and BCWP (Budgeted Cost for Work Performed) using the
Earned Value method. From these parameters, estimate aspects
of cost and time. As well as project analysis of acceleration on a
critical trajectory of work. The results of calculations in the
12th week obtained a BCWS value of Rp 1,216,677,846,400
BCWP = Rp 3,040,372,140,080, ACWP = Rp 3,678,560,000.
CV value = -Rp 109,203,495.92, SV = Rp 895,646,816.82, CPI
= 0.827, and for SPI = 2,499. From these results it can be seen
that the CPI value < 1 which means that there are project
expenditures that exceed the original plan. With the results, it
can be used as a reference in the implementation of project
activities.
Keywords :
Earned Value, Project Delay,
Project Management, Road
Construction
Style IEEE dalam mensitasi
artikel ini:
[1]
B. Damara and R. Hepiyanto,
“Optimalisasi Waktu dan Biaya
Pada Proyek Gedung Pertanahan
Nasional Kota Blitar Dengan
Metode Critical Path Method
(CPM),” J. Manaj. Teknol. Tek.
Sipil, vol. 4, no. 1, pp. 119–133,
2021, doi:
10.1016/j.jksues.2019.09.005.
1. Pendahuluan
Proyek konstruksi jalan merupakan salah satu proyek yang telah berkembang cukup
pesat. Jalan menjadi salah satu sarana transportasi yang berpengaruh terhadap kegiatan
masyarakat. Pembangunan jalan menunjang perkembangan suatu wilayah serta peningkatan
perekonomian. Dengan adanya jalan, mobilitas dalam segala hal menjadi lebih mudah
sehingga akan memberikan dorongan ekonomi yang lebih kuat. Meningkatnya jumlah
kendaraan serta pengguna jalan, harus diimbangi dengan pemeliharaan jalan seperti perbaikan
konstruksi hingga pelebaran jalan. Proyek pelebaran jalan Jombang-Ploso-Legundi-Gresik
menjadi salah satu proyek pembangunan jalan yang dikerjakan di ruas Provinsi jatim. Proyek
Tersedia Secara Online di
http://ojs.unik-kediri.ac.id/index.php/jurmateks/index
http://dx.doi.org/ 10.30737/jurmateks
JURMATEKS