Contents lists available at ScienceDirect
Electric Power Systems Research
journal homepage: www.elsevier.com/locate/epsr
Grid operation-based outage maintenance planning
Guillaume Crognier, Pascal Tournebise, Manuel Ruiz
⁎
, Patrick Panciatici
RTE - Réseau de Transport d’Electricité, Paris La Défense, France
ARTICLE INFO
Keywords:
Energy transition
Maintenance
Planning
Risk
ABSTRACT
The increasing integration of renewable energies in the French electricity network leads to important changes in
its operation, resulting in new grid constraints. Besides, some maintenance tasks on the overhead power lines are
live-line works, and others require a planned outage. Such interruptions may not be feasible with a renewables-
driven grid operation. As a consequence, current maintenance planning methods might not be relevant in the
future. In particular, they have to take into account the risk implied by performing maintenance when having a
high proportion of renewables in the grid. This work presents a three-step approach for tackling this issue. First,
risk values corresponding to diferent future scenarios are computed, using the (N-1) security assessment.
Second, these computed values are included in several optimisation approaches in order to fnd a good schedule.
Eventually, a third step validates the obtained planning.
1. Introduction
Guaranteeing both electricity delivery and supply is one of the most
important mission of a transmission system operator such as RTE. But
such an objective can be carried out only if the grid is correctly main-
tained. In particular, some maintenance operations on the overhead
power lines are live-line works while others require to shut the power
down. When this happens, both electricity delivery and supply have to
be guaranteed, meaning that maintenance operations have to be
planned carefully. Indeed, the security of a grid is by defnition its
ability to survive contingencies [1]. When there is not any maintenance
operation, the (N-1) security assessment rule makes the network re-
silient to an unexpected contingency [2]. However, if several break-
downs are to occur the grid might face major blackouts [3]. In this
context, planned outages due to maintenance work have to be sched-
uled with extreme caution.
Alongside with this very operational aspect, anticipating what
maintenance plannings will look like in the years to come helps in
designing efcient network design strategies. If future maintenance
operations appear to be unfeasible due to an aging network, new gen-
eration and consumption plans or even the energy transition, RTE has
to anticipate these changes and adapt its current maintenance practices
and design, as of today, new strategies.
In the literature, ”outage planning” often refers to the maintenance
of the generation units [4,5], even if occasionally more specifc grid
constraints are taken into consideration [6,7]. Finally, some studies
were conducted in order to fnd optimal outage schedules for both
generating units and transmission networks [8–11]. As RTE is an
electricity transmission operator, this contribution only considers the
maintenance operations on the network as in [12].
Additionally, the ongoing energy transition is leading to new grid
constraints, causing previous maintenance plannings not to be ne-
cessarily feasible in near future. More recent papers studying the unit
commitment problem add the uncertainty coming from renewables. In
order to take these stochastic aspects into account, most of them choose
to model the problem with chance constraints [13,14], multi-stage
optimisation [15] or robust formulations [16].
However, very few papers consider the impact of the energy tran-
sition on maintenance outage planning. An example of such a study can
be found in [17]. Moreover, in all the references cited above the grid
operation is assumed to be known and the uncertainty, if included,
comes from the renewable generation.
This paper’s main contribution is to describe a new methodology
able to account for uncertainty in grid operation. By applying this
methodology to future grid fow scenarios, RTE will be able to con-
solidate the long-term tractability of its current maintenance practices
and network design strategies.
This paper provides technical insights on the problem im-
plementation but the intention is to expose clearly the whole metho-
dology. In particular, strong assumptions that are needed to make the
whole process tractable will be discussed at length in a dedicated sec-
tion.
The mentioned methodology is actually a three-step approach of the
problem. First, fnancial risk values are computed for diferent scenarios
https://doi.org/10.1016/j.epsr.2020.106682
Received 26 September 2019; Received in revised form 27 May 2020; Accepted 1 August 2020
⁎
Corresponding author.
E-mail addresses: pascal.tournebise@rte-france.com (P. Tournebise), manuel.ruiz@rte-france.com (M. Ruiz), patrick.panciatici@rte-france.com (P. Panciatici).
Electric Power Systems Research 190 (2021) 106682
Available online 28 August 2020
0378-7796/ © 2020 Published by Elsevier B.V.
T