Simulation of Lightning Transients on 110 kV
overhead-cable transmission line using ATP-EMTP
Kresimir Fekete
1
, Srete Nikolovski
2
, Goran Knezević
3
, Marinko Stojkov
4
, Zoran Kovač
5
#
Power System Department, Faculty of Electrical Engineering Osijek
K. Trpimira 2B, 31000 Osijek, Croatia
1
kresimir.fekete@etfosr.hr
2
srete.nikolovski@etfos.hr
*
Faculty of Mechanical Engineering Slavonski Brod
I. B. Mažuranić 2, 35000 Sl. Brod, Croatia
4
marinko.stojkov@gmail.com
Croatian Transmission System Operator
K. Franje Shepera 1A, 31000 Osijek, Croatia
5
zoran.kovac@hep.hr
Abstract—Due to construction of a highway in the eastern part
of Croatia, a new 110/x kV substation was built with two parallel
connecting underground cables. Cables were connected to
already existing 110 kV overhead lines. At the place where the
transition between overhead lines and cables is made, surge
arresters were installed. In this paper lightning stroke at the
grounding wire on the overhead line and its impact on
underground cables were studied. Transient program
Electromagnetic Transients Program (ATP-EMTP) is used to
create a model of the system and to perform simulation of the
transient process during lightning stroke. The results of the
simulation are briefly presented and discussed in the paper.
I. INTRODUCTION
In the process of designing new facilities in the power
system (substations, cables, overhead lines etc.), lightning
overvoltages are important from the viewpoint of the
insulation and surge arrester coordination. Due to construction
of the highway in the eastern part of Croatia, a new 110/x kV
substation was built with two parallel connecting underground
cables as well. Cables were connected to already existing 110
kV overhead lines. A more detail presentation of the system is
presented in Chapter II. At the place where the transition
between overhead lines and cables is made, surge arresters
were installed. In order to make surge arrester coordination it
is necessary to investigate the impact of lightning
overvoltages.
It is very hard to observe the lightning overvoltages
experimentally, and thus a numerical simulation is used to
investigate it. The EMTP has been widely used for the time
domain transient solution. It was first developed at Bonneville
Power Administration (B.P.A.) from Dommel’s basic work
[1]. Nearly all system components can be represented by built-
in elements in ATP-EMTP like overhead lines with line and
ground wires and towers as well as underground cables [2]. In
this paper ATP-EMTP is used to create a model of the power
system and to simulate lightning stroke at the grounding wire
on the overhead line and its impact on underground cables and
surge arresters.
The structure of this paper is as follows: first, a brief
explanation, regarding the part of the transmission system
where the new substation and cables are built, is given. The
main features of the ATP-EMTP model and method are
explained in Chapter III. In Chapter IV, simulation and results
are presented. Based on the results, the conclusion is given in
the last chapter.
II. DESCRIPTION OF THE POWER SYSTEM
The part of the Eastern Croatian transmission system that is
studied in this paper is shown in Fig.1. The new substation TS
110/20 kV Djakovo 3 is supplied from two substations TS
220/110 kV Djakovo and TS 400/110 kV Ernestinovo. The
new substation is modelled only with passive load. At the
place where overhead line and cable are connected, ABB
Pexlim Q surge arresters are installed.
Fig. 1. Single line diagram representing the part of the transmission system
that is studied
Parameters of the 110 kV overhead lines which are made of
Al/Fe conductors with cross sections 240/40 mm
2,
and
underground cables type NEXANS which has a cross section
of 1000 mm
2
are shown in Table I.
978-1-4244-5794-6/10/$26.00 ©2010 IEEE 856