Knowledge-Based Standard Progress Measurement
for Integrated Cost and Schedule Performance Control
Youngsoo Jung, A.M.ASCE
1
; and Seunghee Kang
2
Abstract: Though the progress of construction projects is most often used as a critical index for effective project management, the
method, structure, data, and accuracy of detailed progress measurement may vary depending on specific characteristics of a project. This
situation can lead to misinterpretation of the project status, especially under a multiproject management environment. It is also a daunting
task for the inexperienced engineers to formulate and monitor the project-specific work packages. At the same time, maintaining very
detailed and highly accurate progress information requires excessive managerial efforts. In order to address this issue, this study proposes
the concept of standard progress measurement package. Issues for standardization of the work breakdown structure that can embody
distinct characteristics of different construction projects are investigated. The proposed methodology facilitates automated formulating of
work packages by using a historical database and also automates the gathering of progress information through the use of standardized
methods and tools. A case-study project is evaluated in order to examine the practicability of the proposed system.
DOI: 10.1061/ASCE0733-93642007133:110
CE Database subject headings: Cost control; Scheduling; Integrated systems; Information systems; Project management;
Knowledge-based systems; Automation; Standardization.
Introduction
Cost, schedule, and quality are the three major indicators for con-
struction project performance. Accordingly, integration of cost
and schedule control systems has been an issue of great concern
for researchers and practitioners as these two important control
systems are closely interrelated, sharing numerous common data
Rasdorf and Abudayyeh 1991; Jung and Gibson 1999; Jung and
Woo 2004 in their controlling processes.
In recent efforts to systemize construction management
processes, standard methods and procedures coupled with infor-
mation technology have been widely adapted. The earned value
management system EVMS, which integrates cost and schedule
control, is a good example. Two important features of EVMS are
the combination of two different construction business functions
i.e., cost and schedule into a unified perspective and the provi-
sion of highly detailed standard methods and procedures so as to
compulsorily maintain data integrity among many different
project participants Jung and Woo 2001.
The progress or earned value is key information in the inte-
grated cost and schedule control as it provides a baseline for
comparison with the planned schedule and/or actual costs. How-
ever, the method, structure, data, and accuracy of detailed
progress measurements may vary depending on the characteristics
of a project, organization, or location. Regardless of the variation
in the methods utilized, in terms of accuracy, ideally the progress
data should be analyzed and maintained in a highly detailed form.
Nevertheless, the excessive workload required to manipulate very
detailed progress data is also a critical issue Deng and Hung
1998; Rasdorf and Abudayyeh 1991; Jung and Woo 2004 for
effective cost and schedule control.
No previous research or professional practice has comprehen-
sively addressed the issues of standard progress measurement
methodology in terms of its practicability, accuracy, efficiency,
and potentiality for automation. In this context, the purpose of
this study is to develop an effective progress measurement system
utilizing standard progress measurement packages SPMPs, as
depicted in Fig. 1. A prime objective of developing SPMPs is to
identify manageable work packages with reliable progress mea-
surement enhancing accuracy.
Even though those are not addressed in detail, this study also
discusses applying standard measures and procedures to as many
projects as possible so as to attain a corporate-wide index making
standards, facilitating the process of work breakdown structure
WBS formulation by using a prestructured historical database
alleviating workload, and accommodating self-evolving features
of standard packages by analyzing the changes of managerial
policy under an ever-changing business environment sustaining
adaptability.
A case study is used throughout this paper in order to illustrate
and examine the proposed methodology. The case-project is a
research center constructed by a case-company. The research cen-
ter is basically comprised of an eleven-story office building two
stories underground and nine stories above ground and a labora-
tory. Specifics of the project include: 17,087 m
2
of total floor
area, 19-month project duration. A general contractor’s viewpoint
as a case-company is applied in this case-study, and the architec-
tural work alone is analyzed excluding earthwork, mechanical,
1
Associate Professor, College of Architecture, Myongji Univ., Yongin
449-728, South Korea. E-mail: yjung97@mju.ac.kr
2
Ph.D. Candidate, College of Architecture, Myongji Univ., Yongin
449-728, South Korea. E-mail: kshcju@mju.ac.kr
Note. Discussion open until June 1, 2007. Separate discussions must
be submitted for individual papers. To extend the closing date by one
month, a written request must be filed with the ASCE Managing Editor.
The manuscript for this paper was submitted for review and possible
publication on December 19, 2005; approved on July 10, 2006. This
paper is part of the Journal of Construction Engineering and Manage-
ment, Vol. 133, No. 1, January 1, 2007. ©ASCE, ISSN 0733-9364/2007/
1-10–21/$25.00.
10 / JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE / JANUARY 2007