International Journal of Scientific & Engineering Research, Volume 3, Issue 6, June-2012 1
ISSN 2229-5518
IJSER © 2012
http://www.ijser.org
Available Transfer Capability Calculations with
Contingencies for Andhra Pradesh State Grid
Chava Sunil Kumar, Dr. P. S Subramanyan, Dr. J. Amarnath
Abstract— Contingency analysis and risk management are important tasks for the safe operation of electrical energy network. Potential
harmful disturbances that occur during the steady state operation of a power system are known as contingencies. Contingency analysis is
carried out by using repeated load flow solutions for each of a list of potential component failures. In this paper is work is carried out by se-
lecting the contingencies according to the line loading for single transmission line outage and identified the severe most contingency based
on transmission line loading. This process has to be executed for all the possible contingencies for tie lines and limiting lines, and repeated
every time when the structure changes significantly and Available Transfer Capability (ATC) is calculated between the areas f or each con-
tingency. The results are analyzed and discussed on 124-bus real life Indian utility system of Andhra Pradesh State Grid.
Index Terms— Contingency, ATC, Outage, MVA rating, Blackout.
—————————— ——————————
1 INTRODUCTION
NE of the most important factors in the operation of a
power system is the desire to maintain system security.
System security involves practices designed to keep the
system operating when components fail. For example, a gene-
rating unit may have to be taken off-line because of auxiliary
equipment failure. By maintaining proper amounts of spin-
ning reverse, the remaining units on the system can make up
the deficit without too low a frequency drop or need to shed
any load. Similarly, a transmission line may be damaged by a
storm and taken out by automatic relaying. If, in committing
and dispatching generation, proper regard for transmission
flows is maintained, the remaining transmission lines can take
the increased loading and still remain within limit. Because
the specific times at which initiating events that cause compo-
nents to fail are unpredictable, the system must be operated at
all times in such a way that the system will not be left in a
dangerous condition should any credible initiating event oc-
cur. Since power system equipment is designed to be operated
within certain limits, most pieces of equipment are protected
by automatic devices that can cause equipment to be switched
out of the system if these limits are violated. If any event oc-
curs on a system that leaves it opening with limits violated,
the event may be followed by a series of cascading failures
continues, the entire system or large parts of it may complete-
ly collapse. This is usually referred to as a system blackout [1].
An example of the type of event sequence that can cause a
blackout might start with a single line being opened due to an
insulation failure; the remaining transmission circuits in the
system will take up the flow that was flowing on the now-
opened line. If one of the remaining lines is now heavily
loaded, it may open due to relay action, thereby causing even
more load on the remaining lines. This type of process is often
termed a cascading outage. Most power systems are operated
such that any single initial failure event will not leave other
components heavily overloaded, specifically to avoid cascad-
ing failures.
Contingency Analysis (CA), as a part of static security
analysis, is critical in many routine power system and power
market analysis, such as ATC evaluation, security assessment
and transaction arrangement. A typical CA has models, single
element outage (one –transmission line, one generator outage,
etc.), multiple element-outages (two-transmission line outage,
one –transmission line and one generator outage, etc.) and
sequential outage (one outage after another) [3]. In the case of
loss of one component, this corresponds to the N − 1 criterion,
i.e. the system should be able to support the load when one of
the N basic transmission system components (transmission
lines, generators or transformers) is out of operation. The ap-
plication of the criterion can also be extended for the case of
loss of combinations of these basic components. When applied
to the loss of two components, it leads to the N – 2 criterion.
Since a contingency can take place at any instant of operation,
the system design should be such that the system is able to
deal with the worst-case scenario, i.e. the peak load. Limit
checking is done for each contingency to determine whether
the system is secure [4].
With the global towards the deregulation in the power sys-
tem industry, the volume and complexity of the CA results in
the operation and the system studies have been increasing.
Not only has deregulation resulted in much larger system
model sizes, but also CA is computed more frequently in the
restructured power markets to monitor the states of the sys-
tem under ȃwhat ifȄ situations in order to accommodate the
maximum number of power transfers. The net impact of these
changes is a need for more effective CA results are required to
help with the comprehension of the essential security informa-
tion, information which could be buried in the enormous and
complex CA data sets [7], [8].
A 124-bus real life Indian Utility system is considered to
find the variation of ATC between the areas for transmission
line outage of tie-lines. Contingency ranking is taken accord-
ing to the percentage loading of the lines.
O