Construction Management and Economics (January 2010) 28, 35–49
Construction Management and Economics
ISSN 0144-6193 print/ISSN 1466-433X online © 2010 Taylor & Francis
http://www.informaworld.com
DOI: 10.1080/01446190903365632
Simulating the impact of supply chain management
practice on the performance of medium-sized
building projects
JATI UTOMO DWI HATMOKO
1
* and STEPHEN SCOTT
2
1
Department of Civil Engineering, Diponegoro University, Semarang, Indonesia
2
Department of Civil Engineering, University of Newcastle upon Tyne, UK
Taylor and Francis
Received 23 December 2008; accepted 25 September 2009
10.1080/01446190903365632
Construction supply chains encompass the flows of materials, labour, information, plant, equipment and
temporary works that originate from a variety of different parties. The impact of various supply chain
management practices on project performance has been measured, through a combination of a survey and the
development of simulation models. Preliminary investigations were carried out by visiting two medium-sized
building projects regularly over a period of six months to gain an understanding of the ways in which delays
on supply chains impact on project performance. This was followed by the main survey which was designed to
collect data required for developing the simulation models. These models were developed using Pertmaster
Risk Expert
TM
software and incorporated supply chain delays applied to a CPM network of a typical medium-
sized building project of 300 days’ duration. The results of the simulation showed that the project’s median
delay was 67 days (22% of the project duration). The use of subcontractors in the project reduced this delay
by approximately 45%. It was also learned that delays in material flow caused the biggest impact on the project,
followed by labour flow, information flow and ‘plant, equipment and temporary work’ flow. These findings are
an important measure of how much supply chain delays impact on project performance.
Keywords: Supply chain management, supply chain delays, project performance, simulation, risk.
Background
While supply chain management (SCM) in the manu-
facturing industry has developed and been widely
understood for a number of decades, in the construction
industry this approach is a much more recent area of
interest. People in construction, i.e. clients, contractors,
suppliers and subcontractors, are still exploring what
SCM is, how it works to increase competitive advantage
and what are its dynamics (Arbulu and Ballard, 2004).
Supply chains in the construction industry can be
very complex. Large numbers of subcontractors and
suppliers may be involved, especially in a large-scale
project. In a construction project, any delay of the mate-
rials delivery may have knock-on effects on delaying the
works and, if they are critical, the project will likely be
delayed as a consequence. The same situation will also
happen for the late completion of the subcontractors’
works. At a corporate level, the number of parties
involved in the supply chain may increase to thousands
for the whole year.
Current research related to SCM in a construction
context is looking at the issues of: relationships between
contractor, subcontractor and supplier (Kadeforsi,
1999; Greenwood, 2001; Kale and Arditi, 2001),
subcontractor and supplier selection (Kumaraswamy
and Matthews, 2000), organizational perspectives/
network alliances in SCM (London, 2001; Love et al.,
2002), just-in-time (JIT) practice (Akintoye, 1995;
Tommelein and Li, 1999; Tommelein and Weissen-
berger, 1999), construction processes (Nicolini et al.,
2001; Roy et al., 2003), industrial/economic perspective
of SCM (London and Kenley, 2001), communication
and information technology in SCM (Marsh and Finch,
1999; Edum-Fotwe et al., 2001; O’Brien, 2001), risks
in SCM (Tah and Carr, 2001), partnering (Larson,
* Author for correspondence. E-mail: jati.hatmoko@undip.ac.id
Downloaded By: [Hatmoko, Jati Utomo Dwi] At: 01:48 17 February 2010