Pergamon
International Journal of Project Management, Vol. 15, No. 6, pp. 377-387, 1997
© 1997 ElsevierScienceLtd and IPMA. All rights reserved
Printed in Great Britain
0263-7863/97 $17.00+0.00
PII: S0263-7863(96)00088-9
Measuring uncertainty and
criticality in network planning by
PERT-path technique
Giovanni Mummolo
Department of lndustrial Design and Production, Polytechnic of Bari, Viale dapigia 182, 70126 Bari, Italy
The use of uncertainty and criticality measures in network planning of engineering projects by
PERT networks is limited in practice because of their unreliability or complexity. The measures
appear as inappropriate to support the definition of contractual obligations when based on
uncertain information. The author proposes new uncertainty and criticality measures based on
the identification and analysis by PERT-path technique of possible completion sequences of
project activities. The measures prove to be effective in project planning and contracting. An
algorithm and a stochastic analytical model suitable for the quantification of the measures
concerned are proposed. A numerical example is developed. © 1997 Elsevier Science Ltd and
IPMA
Keywords:projectplanning, networktechniques,uncertainty measures
Introduction
Failure risks of an engineering project mainly depend upon
difficulties inherent to the project, human skills, unpredict-
able and uncontrollable events and upon uncertainty of
information on which decisions are based. A relevant
aspect of the last form of risk is the ability of contractual
parties to manage at best information available in technical
documents supporting contract definition. Project planning
is of particular importance in this respect as it contributes to
define contractual technical documents.
The drawing up and agreement on planning marked by
high uncertainty often leads both contractual parties to
commit obligations without full awareness. If the plant is
very complex and its implementation subject to great
uncertainty, owner and contractor often agree to share
failure risks. The goodness of risk appraisal depends on
planning estimates reliability and on planning technique
adopted. Several ways of conceiving project planning exist
and there are as many ways of formalising it. Project
modelling results only in a formal and incomplete
representation of planner's ideas and of risks he perceives.
Yet, once planning has been shared between owner and
contractor, project modelling can lead to contract obliga-
tions. In this phase uncertainty and criticality measures
contribute to estimate project risks. The measures are
widely investigated in the literature concerned. They are,
however, sometimes unreliable, sometimes difficult to
determine, and anyway unsuited at contract stage to
estimating project risks. In this scenario new uncertainty
and criticality measures in project planning and contracting
are needed.
After reviewing main results in the literature concerning
uncertainty and criticality in network planning of projects,
this paper addresses the theoretical framework to define
and calculate new measures for project planning and
contracting.
Uncertainty and criticality measures in network
planning
Criticality and uncertainty measures concerning the evolu-
tion of a project are of varying complexity and reliability
according to the network technique adopted in project
planning.
One of the most widely used techniques is the Critical
Path Method (CPM).I CPM assumes that activity times are
not subject to uncertainty and bases the identification of
project criticality on the slack time allowed for each
activity completion. The attention of planners is mostly
devoted to zero total slack time activities, that it to those
activities belonging to the so called "critical path".
Differently from CPM, PERT assumes that activity time
varies randomly according to probability density functions
(pdfs) which usually are of Beta type. Under the
assumption of statistical independence among activity
times, the pdf of project completion date is determined.
This pdf is assumed to be normal, with expected value and
variance equal to the sum, respectively, of expected values
and variances of activity times belonging to the critical
377