Blast-Induced Liquefaction for Full-Scale Foundation Testing
Scott A. Ashford, M.ASCE
1
; Kyle M. Rollins, M.ASCE
2
; and J. Dusty Lane, M.ASCE
3
Abstract: This paper describes a pilot test program that was carried out to determine the appropriate charge weight, delay, and pattern
required to induce liquefaction for full-scale testing of deep foundations. The results of this investigation confirmed that controlled
blasting techniques could successfully be used to induce liquefaction in a well-defined, limited area for field-testing purposes. The tests
also confirmed that liquefaction could be induced at least two times at the same site with nearly identical results. Excess pore pressure
ratios greater than 0.8 were typically maintained for at least 4 min after blasting. The test results indicate that excess pore pressure ratios
produced by blasting could be predicted with reasonable accuracy when single blast charges were used. However, for multiple blast
charges, measured excess pressures were significantly higher than would have been predicted for a single blast with the same charge
weight. The measured particle velocity attenuated more rapidly with scaled distance than would be expected based on the upper bound
relationship developed from previous case histories. Settlement was typically about 2.5% of the liquefied thickness, and about 85% of the
settlement occurred within 30 min after the blast. Cone penetrometer test results show that blasting initially reduced the soil strength, but
after several weeks the strength had substantially increased.
DOI: 10.1061/ASCE1090-02412004130:8798
CE Database subject headings: Liquefaction; Full-scale tests; Pile foundations; Slope stability; Lateral loads; Blast loads; Blasting;
Deep foundations.
Introduction
The lateral load capacity of deep foundations is critically impor-
tant in the design of bridge structures in seismically active re-
gions. Although fairly reliable methods have been developed for
predicting the lateral capacity of piles in nonliquefied soils, there
is very little information to guide engineers in the design of piles
that are surrounded by liquefiable soils. Certainly, ongoing cen-
trifuge studies using small-scale models e.g., Wilson et al. 2000;
Dobry et al. 1996 are providing valuable insight into soil-pile
interaction in liquefied soil. However, full-scale tests are neces-
sary to verify and calibrate these models and to provide ground
truth information. To improve our understanding of the lateral
load behavior of deep foundations in liquefied soil, a series of
full-scale lateral load tests have been performed at the National
Geotechnical Experimentation Site NGES at Treasure Island in
San Francisco. The ultimate goal of the Treasure Island Liquefac-
tion Test TILT project is to develop lateral load-displacement
relationships for a variety of individual piles and pile groups in
liquefied sand under full-scale conditions. The tests were carried
out using a high-speed hydraulic loading system after the sand
surrounding the piles was liquefied using blasting techniques.
The first step in the testing program was to evaluate the ability
of controlled blasting to produce a liquefied soil layer suitable for
the testing program. Although blast densification has been suc-
cessfully performed for over 50 years in many different soil and
site conditions, site-specific studies are generally recommended
Narin van Court and Mitchell 1995. Therefore, a pilot liquefac-
tion study was designed to determine the optimal charge size,
pattern, and delays required to liquefy the soil to a depth of about
5 m and a radius of 5 m surrounding the foundations. Further-
more, a second objective of the pilot program was to confirm that
the liquefaction testing was repeatable, i.e., that a second blast at
the same site would yield similar results. In order to accomplish
these objectives, a series of controlled blasts were carried out at
three separate locations at the Treasure Island NGES.
It is clear that the process of inducing liquefaction through
controlled blasting compared to that resulting from seismic load-
ing is quite different. In earthquake-induced liquefaction, the
porewater pressure is slowly increased by shear waves propagat-
ing up through the soil. In contrast, in blast-induced liquefaction,
the porewater pressure is almost instantaneously increased by
compression waves generated from the explosion. Blasting pro-
duces higher accelerations and higher frequency ground motions
than an earthquake; nevertheless, the velocity and strain levels are
comparable. Field measurements during blast testing Gohl et al.
2001 and analysis Finn 1978 suggest that the residual excess
pore pressure may largely be due to cyclic shear strains in both
cases. During these experiments, we were not attempting to
model the process leading up to liquefaction during an earth-
quake, but to model soil behavior once liquefaction had been
induced.
Site Characteristics
Treasure Island is a 160-hectare manmade island immediately
northwest of the rock outcrop on Yerba Buena Island in San Fran-
1
Associate Professor, Dept. Structural Engineering, Univ. of
California–San Diego, 9500 Gilman Dr., La Jolla, CA 92093-0085.
E-mail: sashford@ucsd.edu
2
Professor, Civil and Environmental Engineering, Brigham Young
Univ., 368 CB Provo, UT 84602. E-mail: rollinsk@byu.edu
3
Graduate Student Researcher, Civil and Environmental Engineering,
Brigham Young Univ., 368 CB Provo, UT 84602. E-mail:
jdlane@et.byu.edu
Note. Discussion open until January 1, 2005. Separate discussions
must be submitted for individual papers. To extend the closing date by
one month, a written request must be filed with the ASCE Managing
Editor. The manuscript for this paper was submitted for review and pos-
sible publication on February 6, 2001; approved on June 12, 2003. This
paper is part of the Journal of Geotechnical and Geoenvironmental
Engineering, Vol. 130, No. 8, August 1, 2004. ©ASCE, ISSN 1090-
0241/2004/8-798 – 806/$18.00.
798 / JOURNAL OF GEOTECHNICAL AND GEOENVIRONMENTAL ENGINEERING © ASCE / AUGUST 2004