Construction Engineering—Reinvigorating the Discipline
Gregory A. Howell
1
; Glenn Ballard
2
; and Iris Tommelein, A.M.ASCE
3
Abstract: Construction engineering is all about production, and producing something useful is the very reason for projects to exist. How
then to explain why construction engineering has progressively fallen out of focus in construction project management education and
research? For an answer, the development of the discipline of construction management since the 1950s must be understood, a development
that yielded a non-production-oriented approach to project management, one that provides the currently accepted operating system for man-
aging the work in projects. This paper first traces the history of the development of the traditional operating system and related commercial
terms and organizational practices. It argues that traditional practices rest on an assumption that careful development of a project schedule,
managing the critical path, and maximizing productivity within each activity will optimize project delivery in terms of cost and duration.
Subsequently, an alternative operating system, developed and proposed by the Lean Construction community, is described. In contrast to the
traditional approach, lean defers detailed planning until closer to the point of action, involves those who are to do the work in designing
the production system and planning how to do it, aims to maximize project performance (not the pieces), and exploits breakdowns as op-
portunities for learning. The history of this development will be traced in broad strokes. DOI: 10.1061/(ASCE)CO.1943-7862.0000276.
© 2011 American Society of Civil Engineers.
CE Database subject headings: Project management; Construction materials; Construction methods.
Author keywords: Construction operations; Project management; Construction engineering; CPM; Lean construction.
Introduction
Professor Henry Parker at Stanford University completed a report
for the Bureau of Yards and Docks of the US Navy in 1965. His
observation in the third paragraph of the introduction is clear and
bold (Parker 1965).
“This study includes the observation and recordings of hundreds
of jobs. It has reinforced an earlier conclusion that, in general, con-
tractor organizations are abdicating their responsibilities to run their
work efficiently. Procedures for doing the job are, too often, being
controlled by semiskilled supervisors, craftspeople, and laborers.
Management guidance is lacking at the level where many dollars
are actually being wasted. ”
Now 45 years later, little has changed in relation to the way work
is structured—who does what, when, where, and how. The authors
attribute this lack of development to a combination of factors:
• Dominance of the activity centered operating system (ACOS) of
current project management,
• Increased reliance on specialty contractors (this may itself be a
function of the ACOS), and
• Increased technical, organizational, and regulatory complexity
of projects (complexity means both more complicated because
of lots of pieces and complex in the sense that the cause-
and-effect relationships between components or dimensions
of performance are not understood in key areas).
The paper will review the development of ACOS, its relation-
ship with organizational practices and commercial terms as they
developed in the context of the times, and efforts to improve project
performance. It is proposed that the development of a lean operat-
ing system creates new research and practice opportunities for the
discipline of construction engineering.
Domains of Project Delivery
The development of traditional project management and how
practices evolved can be understood and explained in terms of three
domains: operating system, organization, and commercial terms.
These are also listed in Table 1.
Traditional Project Management
How Did the Current Approach to Project Management
Develop?
The roots of current project management lead at least back to
Karol Adamiecki (1866–1933), who developed a “Theory of Work
Harmonization” and a tool for graphical analysis similar to those of
Gantt, the “harmonogram” (Marsh 1975). Peter Morris traces the
development of the critical path method (CPM) back to Adamiecki
and forward to the development of project management applied
today (Morris 1994). Morris details the role of military planning
and the Second World War and how this led to the development
of CPM. There are two commonly understood sources for its
application in construction: program evaluation and review tech-
nique (PERT), the probabilistic approach used by the U.S. Navy
for contract control, and the deterministic approach developed
by E. I. DuPont de Nemours and Sperry-Rand Corporation.
The U.S. Navy’ s Bureau of Yard and Docks contracted
with Stanford in the late 1950s to report on “The Application of
1
Executive Director, Lean Construction Institute (corresponding author).
E-mail: ghowell@leanconstruction.org
2
Director, Project Production Systems Laboratory, Civil and Environ-
mental Engineering Dept., Univ. of California—Berkeley, Berkeley, CA.
E-mail: ballard@ce.berkeley.edu
3
Director, Project Production Systems Laboratory; and Professor,
Environmental Engineering Dept., Univ. of California Berkeley, Berkeley,
CA. E-mail: tommelein@ce.berkeley.edu
Note. This manuscript was submitted on June 24, 2010; approved on
August 18, 2010; published online on August 1, 2010. Discussion period
open until March 1, 2012; separate discussions must be submitted for in-
dividual papers. This paper is part of the Journal of Construction Engi-
neering and Management, Vol. 137, No. 10, October 1, 2011. ©ASCE,
ISSN 0733-9364/2011/10-740–744/$25.00.
740 / JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE / OCTOBER 2011
J. Constr. Eng. Manage. 2011.137:740-744.
Downloaded from ascelibrary.org by UNIVERSITY OF CALIFORNIA on 11/28/12. Copyright ASCE. For personal use only; all rights reserved.