Rework in Civil Infrastructure Projects:
Determination of Cost Predictors
Peter E. D. Love
1
; David J. Edwards
2
; Hunna Watson
3
; and Peter Davis
4
Abstract: Within Australia, civil engineering works continue to meet the insatiable demand for new infrastructure despite project
complexity and cost and schedule overruns. A significant factor that can contribute to such overruns is rework; yet to date research into
the root causes and consequential costs of rework in civil infrastructure projects has been limited. Using a questionnaire survey, rework
costs and probable causes were obtained from 115 civil infrastructure projects. Stepwise multiple regression was then used to determine
the significant variables that contributed to rework. The regression model revealed that the following five significant predictors accounted
for 25% of the variance in total rework cost: 1 ineffective use of information technologies; 2 excessive client involvement in the
project; 3 lack of clearly defined working procedures; 4 changes made at the request of the client; and 5 insufficient changes initiated
by the contractor to improve quality. The findings also revealed that mean total rework costs were 10% of the contract value for the
sample. Interestingly, the extent of rework experienced was significantly correlated with project cost and schedule growth p 0.01. It is
suggested that future work is required to determine the underlying factors that contribute to rework in civil infrastructure projects before
effective preventive strategies can be identified.
DOI: 10.1061/ASCECO.1943-7862.0000136
CE Database subject headings: Infrastructure; Construction costs; Australia.
Author keywords: Civil infrastructure; Rework; Stepwise regression; Cost predictors.
Introduction
Rework is a major contributor to cost and schedule growth in
building construction projects Love 2002. The direct costs of
rework are considerable and have been reported to be in excess of
15% of the contract value Construction Industry Development
Agency CIDA 1995; Barber et al. 2000. Historically, research
conducted has predominantly focused on rework in building con-
struction projects e.g., Josephson and Hammarlund 1999; Love
and Li 2000; Love and Edwards 2005 with only limited studies
examining its incidence in civil infrastructure projects e.g., Bu-
rati et al. 1992; Abdul-Rahman 1993; Nylén 1996; Barber et al.
2000; Robinson-Fayek et al. 2004. Past studies that have exam-
ined rework on civil infrastructure projects have been based on
limited data sets which eschew generalizations being made.
Moreover, the varying interpretations and definitions of rework
have led to a lack of uniformity in rework data collation Love
and Smith 2003. A comprehensive methodology to determine
rework costs developed by Robinson-Fayek et al. 2004 is note-
worthy; while this is encouraging, the technique is tedious to use
in practice and cannot yield significant findings with regard to
rework cost predictors. To gain an insight into the causal predic-
tors of rework for civil infrastructure projects, the views and per-
ceptions of industry practitioners were collected using data
obtained from recently completed projects. Questions posed to
practitioners were referenced to, and initially based upon, the
causes of rework on building construction projects; a detailed
review of these can be found in Love et al. 2004, Robinson-
Fayek 2004, and Love and Edwards 2005.
Research Approach
The research approach undertaken by Love 2002 to examine
rework in building construction projects is adopted for the study
reported in this paper. Rework is defined in this research work as
“the unnecessary effort of redoing a process or activity that was
incorrectly implemented the first time” Love 2002. Rather than
simply developing a questionnaire survey that sought respon-
dents’ general opinions about rework, respondents were asked to
select a recently completed project most familiar to them. The
questionnaire then sought to elicit information about the inter-
viewees’ perceived causes or rework, associated costs, and project
management practices implemented. This had the effect of enrich-
ing the data so that a more meaningful analysis could be com-
pleted.
Questionnaire Survey
Stratified random sampling was used to select the study sample
from the telephone directory, Yellow Pages, for the various re-
1
Chair Professor of Construction Management, Dept. of Construction
Management, School of Built Environment, Curtin Univ. of Technology,
GPO Box 1987, Perth, Western Australia 6845, Australia. E-mail:
p.love@curtin.edu.au
2
Senior Lecturer, Dept. of Civil and Building Engineering,
Loughborough Univ., Loughborough, Leicestershire LE11 3TU, U.K.
corresponding author. E-mail: d.j.edwards@lboro.ac.uk
3
Research Assistant, Dept. of Construction Management, School of
Built Environment, Curtin Univ. of Technology, GPO Box 1987, Perth,
Western Australia 6845, Australia. E-mail: h.watson@curtin.edu.au
4
Head of School, Professor of Construction Procurement, School of
Built Environment, Curtin Univ. of Technology, GPO Box 1987, Perth,
Western Australia 6845, Australia. E-mail: p.davis@curtin.edu.au
Note. This manuscript was submitted on April 10, 2008; approved on
August 17, 2009; published online on February 12, 2010. Discussion
period open until August 1, 2010; separate discussions must be submitted
for individual papers. This paper is part of the Journal of Construction
Engineering and Management, Vol. 136, No. 3, March 1, 2010.
©ASCE, ISSN 0733-9364/2010/3-275–282/$25.00.
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE / MARCH 2010 / 275
J. Constr. Eng. Manage. 2010.136:275-282.
Downloaded from ascelibrary.org by Curtin Univ of Technology 2009 on 04/22/14. Copyright ASCE. For personal use only; all rights reserved.