International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 3394
Comparative Study on Cost Estimation of GFRG Wall Panel System with
Conventional Building
Siddhant Singhal
1
, Bilal Siddiqui
2
1
M.Tech. Student, Dept. Of Civil Engineering, Babu Banarasi Das University, Uttar Pradesh, India
2
Assistant Professor, Dept. Of Civil Engineering, Babu Banarasi Das University, Uttar Pradesh, India
---------------------------------------------------------------------***----------------------------------------------------------------------
Abstract - Being a civil engineer it is our priority to provide
cost effective solutions to our clients. With the escalating
prices, the houses are becoming unaffordable with the current
technology and hence we needed to explore another types of
construction systems to reduce the cost of construction. This
paper is an attempt made to give an idea as to how can we
reduce the construction cost as well as reduce the construction
time using the prefabrication technology. This review paper
compiles and retrospect the developments in the field of
prefabricated building systems using GFRG construction
technology also known as Rapidwall© construction
technology in India. Glass fiber reinforced gypsum panels,
manufactured in standardized parts are sections prepared for
rapid erection of buildings, as they are ready-made gypsum
structural panels with hollow cavities. This Rapidwall is
employed in residential as well as commercial constructed
establishments. GFRG walls can be used both for esthetical as
well as structural component as walls and slabs, with no
external columns and beams needed. It has currently found
great utilization, even without exercising complicated codes of
structural design, largely for the reason that they are
environmental friendly. For the cost comparison, the
fundamental materials considered were three types of building
construction method such as low cost building using
prefabrication technology as GFRG wall panel system and
Conventional building construction systems like SMRF
structure and Load bearing wall structure. Costs of these
building materials were collected from contractors of the
nearby areas. The focus in this paper is comparative study on
cost estimation between prefab system (GFRG) and
conventional building systems.
Key Words: Cost Comparison, GFRG, Prefabrication,
Construction, Wall panels, Rapidwall, New building
system, etc...
1. INTRODUCTION
In this new era of construction, several different building
systems orientated for housing appeared in India. Most of
these systems were introduced from first world countries
and many were not able to fit into the Indian construction
standards. This incursion of technology was originated after
the announcement of the reconstruction plan for affected
areas due to El Nino phenomena and Nazca earthquake. On
the other hand, many of these systems were functional in
countries lacking earthquake trouble and the majority of
them employed foreign supplies. In this case of India,
structural systems were supposed to be designed according
with earthquake standard E-030 of the National Building
Code. On the other hand, Indian researchers in the last 20
years developed different solutions for building systems
using locally available materials and most of them were
tested and had the approval and registration of BMTPC.
The present work introduced five construction systems that
are approved by BMTPC. The economic issues are also the
main reason for these different building systems. So we have
to select the most viable and low cost construction for avoid
the financial problems.
2. OBJECTIVE
The purpose of this paper focuses on views of the
construction industry about the difference of the two building
methods such as GFRG (Glass Fiber Reinforced Gypsum) wall
panel system and conventional building construction system
of SMRF structure and load bearing wall structure based on
the estimation value and we have to generate some
construction management results. We have to accumulate
properties and cost details of the building materials.
Comparing the methods, details were taken of cost and time
duration for finishing each construction activity.
3. CONVENTIONAL BUILDING WORK
The major bulk of building construction work is small
renovation, such as addition of a room, or renovation of a
restroom. Often, the owner of the property work as the
introspect, paymaster, and design team for the entire project.
Although, all building construction projects consist of some
elements in general – design, financial, estimation and legal
considerations. Many projects of different sizes reach
unwanted consequences, such as structural failure, cost
overruns, and/or lawsuits. Due to such reasons, those with
expertise in the field make comprehensive plans and keep
cautious supervision throughout the project to ensure a
positive result.
Commercial building construction is procured privately or
publicly utilizing various delivery methodologies, including
cost estimating, hard bid, negotiated cost, conventional,
organization contracting, construction management-at-risk,
design & build and design-build bridging.