Vol. 16 No. 2 Edisi Oktober 2019 ISSN (Online) : 2655-2124
Jurnal Ilmiah Rekayasa Sipil
Available online at : http://ejournal2.pnp.ac.id/index.php/jirs/
Terakreditasi SINTAPeringkat 5
92
InformasiArtikel
Diterima Redaksi : 09-09-2019 | Selesai Revisi : 28-10-2019 | Diterbitkan Online : 31-10-2019
Analisa Harga Satuan Pekerjaan Beton Bertulang Berdasarkan BCWP
dan AHSP SNI 2016 (Proyek Pembangunan Aeon Mixed Use
Apartemen 3 Sentul City Bogor)
1)
Monika Natalia,
2)
Fauna Adibroto,
3)
Desmon Hamid,
4)
Mafriyal Muluk,
5)
Rahma Dinna
1), 2), 3), 4), 5)
Program Studi Teknik Sipil Politeknik Negeri Padang
Email : monikanatalia75@gmail.com, fauna_adibroto@yahoo.com, desmon_hamid@yahoo.co.uk,
mafriyalmuluk60@gmail.com, rahmadinna19@gmail.com
Abstrak
Hasil analisa biaya pekerjaan beton bertulang pada kolom, balok, dan pelat lantai sesuai dengan analisa
pihak kontraktor dengan menggunakan metoda Budgeted Cost of Work Performed didasarkan pada laporan harian
proyek, estimasi pekerja dan alat yang digunakan sesuai dengan kondisi lapangan didapatkan Rp. 2.899.987.012,-.
Hasil perhitungan estimasi biaya pekerjaan beton bertulang pada kolom, balok, dan pelat lantai dengan
menggunakan metoda AHSP SNI 2016 menggunakan software Microsoft Excel didapatkan sebesar
Rp.4.872.399.540,34,-. Selisih biaya total pekerjaan beton bertulang pada kolom, balok, dan pelat lantai kedua
metode ini adalah sebesar Rp.1.972.412.528,-. Penggunaan estimasi biaya pihak kontraktor dengan menggunakan
metoda Budgeted Cost of Work Performed didapatkan hasil yang lebih rendah dari pada analisa AHSP SNI 2016.
Kata Kunci : estimasi biaya, RAB (Rencana Anggaran Biaya), AHSP SNI 2016, Budgeted Cost of Work
Performed, harga satuan, beton bertulang.
©2019 Jurnal Ilmiah Rekayasa Sipil
Abstract
The results of the analysis of the cost of reinforced concrete work on columns, beams, and slabs are in
accordance with the analysis of the contractor using the Budgeted Cost of Work Performed method based on the
project's daily report, estimation of workers and equipment used in accordance with field conditions. 2.899.987.012, -.
The results of the calculation of the estimated cost of reinforced concrete work on columns, beams, and floor slabs
using the 2016 SNI AHSP method using Microsoft Excel software were obtained at Rp..4.872.399.540,34, -. The
difference in the total cost of reinforced concrete work on the columns, beams, and floor slabs of these two methods
is Rp.1.972.412.528. The use of contractor cost estimates using the Budgeted Cost of Work Performed method has
lower results than the 2016 SNI AHSP analysis.
Keywords: estimated costs, RAB (Cost Budget Plan), SNI AHSP 2016, Budgeted Cost of Work Performed,
unit price, reinforced concrete.
1. PENDAHULUAN
Pekerjaan beton bertulang merupakan
faktor penentu dari pembangunan suatu proyek
gedung, dimana pada pekerjaan beton bertulang
tersebut memiliki volume pekerjaan yang besar
diantara pekerjaan yang lain. Untuk itu, selaku
kontraktor yang akan mengikuti tender dan
sedang membuat dokumen penawaran harus
lebih detail dalam menganalisa harga satuan
pekerjaan. Sehingga hasil perhitungan analisa
harga satuan pekerjaan didapatkan lebih efektif
dan efisien dengan harga yang rendah.
Permasalahan yang selama ini sering kali dilihat
bahwa kontraktor membuat analisa harga
satuan pekerjaan mendekati dengan analisa