Utility Management on Major Road Mumbai
A.D. Gavhane
1
, Dr. A.W. Dhawale
1
Student, ICOER, Pune, Maharashtra, India
2
Proffesor, ICOER, Pune, Maharashtra, India
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - In Mumbai, Pipelines/Cables of almost all
utilities are laid underground, generally below the road
surface including the Carriage way and Footpaths. By virtue of
increase in population and living standard, the demand for
services has not just increased, but also citizen expect quality
and prompt services from the Municipal Corporation and all
other service providers. The services with pipeline or cables
laid underground are basically, water supply, drainage,
electric supply, telecommunication, gas line, etc. These services
have caused great congestion below the road surface, thereby
laying of new pipeline or cables has become difficult and
occurrence of faults requiring excavation for carrying out
repairs has increased. There is not a single day when roads are
not excavated for either providing utilities or attending faults
of services.
Some utilities in Mumbai are very old of @ 100 years. Utilities
services with their age deteriorate due to lack of information
about existence of old utilities. It is difficult to trace them
underground since the visual inspection of the underground
utilities is not possible. It is hard to determine and to estimate
when to rehabilitate or replace these utilities. There are
problems concerning underground utilities due to uncertainty
of the location of the utilities. This problem is leading to
delays, extra work orders, change orders, construction claims,
contingency bidding, loss of service, property damage, etc. This
lead to understand and study of new system to be formed to
sustained the growth of utilities in Mumbai city.
Key Words : (Utilities, Services, Ducting, Trenching, etc.)
1. INTRODUCTION
Indian urban cities are seen with high growth in
population, real estate and infrastructure. Cities are
expanding horizontally and vertically to cope up with the
urban requirements and development projects are also
increasing in urban cities. With increase in the development
requirements of cities, utility services like electricity,
telephone, water distribution, sewerage distribution, gas
lines are also increasing. Day by day utilities providers are
increasing making competition among themselves to satisfy
consumer needs.
All utilities in Mumbai are running below road crust
in zigzag manner. Roads are often dug for making new
provisions and maintenance of existing utility services,
causing damage to the road crust causing many problems
related to road maintenance. There are more than 11
utilities department including government utilities in
Mumbai having utility services to consumers.
There are limitations to the co-ordination of utility
service providers among themselves. Therefore it is
proposed that, through study of the existing systems of
utility services to understand difficulties that exist in utility
service providers and to come up with solutions for the
service providers, so as to cause limited damage to the roads
surface.
2. SHORTCOMINGS AND PROBLEMS FACED DUE
TO EXISTING SYSTEM OF LAYING UTILITIES.
2.1 Open excavation of roads
Almost all the utilities lay their cables/pipes by openly
excavating the road up to certain depth. Open excavation
disturbs the original strata of the road, which after
reinstatement do not match with the original standards.
During open excavation, there is chance of damaging the
already laid utilities. Damage to certain utilities like High
tension cables, Gas pipelines, etc. may lead to serious
accidents.
2.2 Uncertainty of locations
In Mumbai certain utility agencies have GPS/GIS system for
locating their cables/pipes. But there are maximum service
providers which do not have system of GPS/GIS for their
networks. Hence during attending faults or repair work,
unnecessary extra area of roads gets excavated due to not
knowing the exact location of the concerned utility.
2.3 Non co - ordination between Utility Agencies
Very few utility agencies in Mumbai have their co-ordination
during laying of their utility networks. Basically all the utility
agencies are supposed to have regular meetings among
themselves for their problems of networks. This is not
followed properly. This causes frequent excavations of the
same stretch of the roads by different utilities. This is the
major cause for the failure of the crust of roads.
2.4 Delays in reinstatement of trenches
Once the work of laying of utility is completed, reinstatement
of trench should start immediately. It is seen that the
reinstatement of trenches works are delayed in Mumbai, this
is because, procurement of material for reinstatement in
advance is not possible due to lack of space available on
roads. Excavating agencies and reinstatement agencies are
different and sometimes reinstatement agencies are not