© 2019 |Published by Scholars Middle East Publishers, Dubai, United Arab Emirates 84
Saudi Journal of Civil Engineering
Abbreviated Key Title: Saudi J Civ Eng
ISSN 2523-2657 (Print) |ISSN 2523-2231 (Online)
Scholars Middle East Publishers, Dubai, United Arab Emirates
Journal homepage: https://scholarsmepub.com/sjce/
Original Research Article
Comparative Study of Prospective Delay Analysis Techniques (DATs)
Suroj Ghimire
1
, Anjay Kumar Mishra
2*
1
NP Associates Pvt Ltd, Project controller, Nepal
2
Associate Professor, Madan Bhandari Memorial Academy, Urlabari, Nepal
DOI: 10.36348/SJCE.2019.v03i05.001 | Received: 15.08.2019 | Accepted: 05.09.2019 | Published: 11.09.2019
*Corresponding author: Anjay Kumar Mishra
Abstract
Delays are the major sources of disputes and adverse relationships between the stakeholders in construction industry. The
existing delay analysis techniques (DATs), though helpful for decision-making, have not succeeded in properly
addressing the high incidence of disputes associated with delay claims resolutions. This research has made a comparative
study of limitation and capabilities of different ‗Prospective‘ DATs i.e., Impacted as Planned method and Time Impact
Analysis Method under the same baseline program and under similar circumstances of delay occurrence through the case
study of under-Construction Hydroelectric Project and review of the relevant issues not addressed by the techniques.
Oracle‘s Primavera (P6) software has been used for delay analysis. The Contractor has not followed any of the DATs to
raise the claim for extension of time. Though the contractor has submitted its revised construction schedule as per the
FIDIC conditions of contract and ask for time extension of 721 days, the revised construction schedule has no any
linkage with the original approved baseline Schedule. The Impacted as planned technique confined the delay to 621 days.
The actual site condition and the progress were not considered in this method. The concurrent delays and pacing delays
were also not addressed. According to the Time Impact analysis technique, the contractor‘s caused delay was 101 days
and the delay from Employer‘s side was 529 days. The actual site condition and the progress were considered in this
method. However, none of the Delay analysis techniques is found to address all the delay occurring events. The
concurrent delays and pacing delayswere also not addressed. Time impact analysis technique is more accurate method as
the site progress is incorporated in this method and is recommended to be followed.
Keywords: Impacted as Planned, Time Impact, Actual site Condition.
Copyright @ 2019: This is an open-access article distributed under the terms of the Creative Commons Attribution license which permits unrestricted
use, distribution, and reproduction in any medium for non-commercial use (NonCommercial, or CC-BY-NC) provided the original author and source
are credited.
INTRODUCTION
BACKGROUND
Construction delays are a main source of
claims and disputes and have even been considered as
the most common and costly cause of problems.
Construction delays impart adverse impact on the
success of the project in terms of time and cost. Its
effect is confined not only to the construction industry
alone, but also to the overall economy of a nation.
To substantiate the delay in Mega project is
very complexin itself. The different methods that are
used to provedelays, as explained in industry standards
and handbooks, are theoretical and could be applied
inthe small simple projects with few numbers of
activities but the same methods cannot easily beapplied
on mega/complex projects [1].
Barry [2], in his paper, presented on the
international conference by the Society of Construction
Law, mentioned that Impacted as-planned method,
Time impact analysis method, Collapsed as-built or
‗but-for‘ analysis method, Snapshot/windows/ time
slice analysis method, As-planned versus as-built
windows analysis methods are commonly used delay
analysis techniques. Inspite of the availability of these
techniques, the most appropriate way to analyze the
delays and causes of delay is still arguable subject.
Arditi and Pattanakitchamroon [3] claimed that that
none of the identified delay analysis methodology can
be universally used in all situations, although they noted
that the Windows Analysis/Time Impact Analysis is the
most acceptable method and provides the most reliable
results. Researchers have identified multiple factors
affecting the selection and the results of the delay
analysis methodology.
The assessment to raise the claim for extension
of time is one of the serious issue. The Baseline
Schedule is an important tool whereby delays are
impacted in a systematic approach to find out the
overall delay occurred in projects. Basically, the DATs