Effects of the application of activity calendars on the distribution of
project duration in PERT networks
Miklós Hajdu
Department of Construction Management, Ybl Miklós Faculty of Architecture and Civil Engineering, Szent István University, Budapest, Hungary
abstract article info
Article history:
Accepted 26 May 2013
Available online 27 June 2013
Keywords:
PERT
Distribution of project duration
Activity calendars
Monte Carlo simulation
The Program Evaluation and Review Technique (PERT) has been criticized for the proposed (beta) distribu-
tion of the activities, the three-point estimation method, the assumption of task independence and the as-
sumed distribution of the project duration since its birth. Developments and generalizations of the
succeeding years and decades were mostly aimed at resolving these issues. However, there are still pending
questions that have not been examined in detail, if at all. One of these issues is the effect of activity calendars
on the distribution of the project duration. Using a simple artificially created project we prove that the appli-
cation of activity calendars has a greater influence on the distribution of the project duration than any of the
above-mentioned criticisms. In the absence of analytic solutions, a robust tool performing Monte Carlo sim-
ulations has been used for calculations.
© 2013 Published by Elsevier B.V.
1. An overview of the Program Evaluation and Review Technique
1.1. Introduction
In this paper, we examine the effect of activity calendars on the
distribution of the project duration in PERT networks. We prove –
using an artificially created sample project – that the original PERT
methodology, which assumes normal distribution for the project du-
ration, cannot be used, due to the distorting effects of activity
calendars.
The paper is organized in the following way:
• Section 1 shortly summarizes the basic concept of PERT in order
to make the paper understandable for those who are not experts
of PERT.
• Section 2 gives an overview of the main criticisms addressed to
PERT.
• Section 3 shortly introduces the principles of the Monte Carlo simula-
tion, and describes the possibilities and limitations of the tool used to
prove the main assertion of the paper, which will be discussed in
Section 4.
• Section 4 is dealing with the effects of the calendars on the probabil-
ity distribution of the project duration. To the best of our knowledge,
no research paper has dealt with this issue yet.
• Section 5 provides the conclusions of the research and recommenda-
tions for further research.
1.2. Introduction to PERT
The original Program Evaluation and Review Technique (PERT) [1]
is an activity-on-arrow network with one start and one finish event,
which represent the beginning and the end of a project. To accomplish
the project, certain activities must be carried out according to a given
pre-defined sequence. This logic is depicted by a directed, acyclic
graph in which the vertices of the graph represent the events, while
the arrows represent the tasks to be performed. An event occurs
when all preceding activities have been completed; only then can
the succeeding tasks start. In this way, the event is used for expressing
logical dependencies between activities.
In a PERT network, activity durations are defined by stochastic
variables that are assumed to be independent of each other. The dis-
tribution of the activity durations follows a so-called PERT-beta dis-
tribution. The formula of the beta function is shown below (Eq. (1)).
In the formula, α and β are the parameters of the beta distribution,
and a and b are the endpoints of the domain of x. Outside the interval,
f(x) = 0. There is also a special case: if α = 1 and β = 1, then f(x)
follows a uniform distribution on the defined domain of x. Possible
density functions of the beta distribution for which a = 0 and b =
1 are shown in Fig. 1. The distribution is identified as PERT-beta if
Automation in Construction 35 (2013) 397–404
E-mail address: hajdu.miklos@ybl.szie.hu.
0926-5805/$ – see front matter © 2013 Published by Elsevier B.V.
http://dx.doi.org/10.1016/j.autcon.2013.05.025
Contents lists available at ScienceDirect
Automation in Construction
journal homepage: www.elsevier.com/locate/autcon