JOS - MRK Volume 1, Nomor 2, September 2020, Page 91-97 91 Journal homepage: http://jos-mrk.polinema.ac.id/ ISSN: 2722-9203 (media online/daring) STRATEGI DAN METODE PELAKSANAAN PEKERJAAN STRUKTUR ATAS PROYEK APARTEMEN ADHIGRYA PANGESTU MARGONDA RAYA, DEPOK Muhammad Zulfikri Afandi 1 , Moch. Khamim 2 , Armin Naibaho 3 Mahasiswa Manajemen Rekasaya Konstruksi, Jurusan Teknik Sipil, Politeknik Negeri Malang 1 , Dosen Jurusan Teknik Sipil, Politeknik Negeri Malang 2 , Dosen Jurusan Teknik Sipil, Politeknik Negeri Malang 3 Email: zulhamfikry18@gmail.com 1 , chamim@polinema.ac.id 2 , ar_naibaho@yahoo.com 3 ABSTRAK Proyek pembangunan Apartemen Adhigrya Pangestu Margonda Raya Kota Depok memiliki luas bangunan 30.200 m 2 berada di atas lahan seluas 4.500 m 2 dan memiliki kontrak 500 hari kalender. Proyek high rise building ini terletak di tengah Kota Depok dan terdiri dari 22 lapis lantai. Pekerjaan struktur merupakan salah satu pekerjaan yang paling utama dalam sebuah proyek pembangunan high rise building, dengan demikian perencanaan strategi dan metode pelaksanaan yang tepat akan menunjang proses pekerjaan sehingga dapat berjalan sesuai dengan target waktu, biaya, dan mutu yang telah disyaratkan. Perencanaan strategi dan metode pelaksanaan bertujuan untuk mengetahui bagaimana suatu proyek dilaksanakan dengan pembuatan langkahlangkah berupa flowchart tahap pelaksanaan yang disertai dengan deskripsi dan diilustrasikan menggunakan gambar visual rencana sehingga dapat mengetahui kebutuhan komponen proyek berupa alat, material, dan tenaga kerja yang akan dipakai secara sequence untuk setiap pekerjaan. Item pekerjaan struktur pada proyek Apartemen Adhigrya Pangestu ini adalah pekerjaan kolom, balok, pelat, shear wall, dan tangga. Dari hasil studi, jam kerja pada proyek ini direncanakan selama 12 jam dengan rincian pekerjaan struktur dibagi menjadi dua zona kerja berdasarkan kapasitas layanan alat berat yaitu tower crane. Durasi pelaksanaan direncanakan 420 hari kerja dengan total anggaran biaya pelaksanaan sebesar Rp. 137.702.963.000,00. Kata kunci: strategi metode; struktur atas; alat; material ABSTRACT The construction project of the Adhigrya Pangestu Margonda Raya Apartment in Depok City has a building area of 30,200 m 2 on an area of 4,500 m 2 and has a 500 days calendar contract. This high rise building project is located in the middle of Depok city and consists of 22 floors. Structural work is one of the most important jobs in a high rise building development project, so that strategic planning and proper implementation methods will support the work process so that it can run according to the required target time, cost and quality. Strategic planning and implementation methods aim to find out how a project is implemented by making steps in the form of a flowchart for the implementation stage accompanied by descriptions and illustrated using visual plans so that you can find out the needs of project components in the form of tools, materials and labor that will be used in sequence for every job. The structural work items in the Adhigrya Pangestu Apartment project are column, beam and plate work, shear walls and stairs. From the results of the arrangement, the working hours on this project are planned for 12 hours with details of the structural work divided into 2 work zones based on the service capacity of heavy equipment, namely tower cranes. The implementation duration is planned for 420 working days with a total budget for implementation costs of Rp. 137,702,963,000,00. Keywords: strategy methods; upper structure; tool; materials 1. PENDAHULUAN Proyek Pembangunan Apartemen Adhigriya Pangestu merupakan proyek gedung bertingkat tinggi yang terletak di Kota Depok. Proyek tersebut berada di jalan utama yaitu Jalan Margonda Raya yang merupakan jalan penghubung antara Kota Depok dan Kota Bogor dengan arus lalu lintas yang sangat padat. Proyek ini memiliki luas bangunan 30.200 m 2 . Proyak ini dibangun di atas lahan seluas 4.500 m 2 dan memiliki kontrak 500 hari kalender. Proyek high rise building ini terdiri dari 22 lapis lantai yang merupakan beton bertulang dengan rincian pekerjaan kolom, balok, pelat lantai, shear wall, dan tangga.