Bolted shear connectors vs. headed studs behaviour in push-out tests
Marko Pavlović
a,
⁎, Zlatko Marković
a
, Milan Veljković
b
, Dragan Buđevac
a
a
Faculty of Civil Engineering, University of Belgrade, Serbia
b
Luleå University of Technology, Sweden
abstract article info
Article history:
Received 8 February 2013
Accepted 4 May 2013
Available online 2 June 2013
Keywords:
Steel–concrete composite beams
Prefabricated structures
High strength bolts
Headed studs
Shear connector height
Parametric study
Push-out tests
Finite element analysis
Damage plasticity
Prefabrication of concrete slabs reduces construction time for composite steel–concrete buildings and brid-
ges. Different alternatives for shear connectors (bolts and headed studs) are analysed here to gain better in-
sight in failure modes of shear connector in order to improve competiveness of prefabricated composite
structures. Casting of high strength bolted shear connectors in prefabricated concrete slabs offers the higher
level of prefabrication comparing to a standard method of grouting welded headed studs in envisaged
pockets of concrete slabs. In addition, bolted shear connectors can easily be dismantled together with the
concrete slab thus allowing the improved sustainability of the construction, simpler maintenance, and devel-
opment of modular structural systems. Bolted shear connectors have been rarely used in construction, actu-
ally just for rehabilitation works, because there is a lack of design recommendation. The first step towards the
design recommendation is to understand the difference between the headed shear studs and the bolted shear
connectors in a push-out test. Push-out tests, according to EN1994-1-1, using 4 M16 — grade 8.8 bolts with
embedded nut in the same layout and test set-up as for previously investigated headed studs were
performed. Finite element models for both shear connectors were created, and good match with experimen-
tal data was obtained. Basic shear connector properties such as: shear resistance, stiffness, ductility and fail-
ure modes have been compared and discussed in detail by using experimental and FE results. Parametric FE
analyses of shear connector's height are carried out and shear resistance reduction factor has been proposed
for bolted shear connectors.
© 2013 Elsevier Ltd. All rights reserved.
1. Introduction
Steel–concrete composite beams have been used in buildings and
bridges for decades. In-situ casted concrete requires often temporary
supports and formwork which leads to a longer construction time
compared to, recently established, prefabricated concrete slabs. Pre-
fabrication of concrete slabs is a good way to reduce the construction
time and optimize construction process. Composite action between a
steel profile and a concrete slab is most commonly established by
grouting grouped headed studs welded to a flange of steel section
in envisaged openings (pockets) of prefabricated concrete slabs.
Moreover, if the replacement of concrete slabs is required either for
structural reasons (maintenance) or practical reasons (end of the
life time), bolted shear connectors has big advantages because of
easier dismantling.
Prefabricated composite deck structures with bolted shear connec-
tors may be used in residential and commercial buildings, car parks
and modular building systems. They can also be competitive for short
span overpass bridges and modular temporary bridge systems. Dry as-
sembling and faster erection process are obtained by casting bolts in
prefabricated concrete slabs and by on-site assembling into predrilled
flange of steel section part of composite member. In this case, low fabri-
cation tolerances of prefabricated elements need to be achieved so as to
ensure assumed composite action of the structure.
Tolerances for the concrete slabs in prefabricated bridges are rather
strict and very good state of the art on the requirements, achieved toler-
ances and costs are provided in Hällmark licentiate thesis [1]. Reference
is made to a match casting technique in order to get sufficient precision.
This technique means that the first element can be cast in an ordinary
formwork, but from the second element and further, the previous cast
element should be used as formwork on one side of the next element.
By using this match-casting technique it has been shown that it is pos-
sible to keep the mean joint-gap ≤ 0.4 mm as achieved in the single
span L = 28 m, prefabricated composite road bridge AC 1684 built in
2002 in Norrfors, Sweden. The total cost of the prefabricated bridge
was smaller than the in-situ cast bridge, in spite of such small execution
tolerances achieved.
The construction costs with use of bolted shear connectors are
expected to be higher when compared to traditional headed studs.
Still, the faster erection and life cycle cost analysis may lead, for cer-
tain applications, that the total economy of the precast structures be-
comes competitive. However, bolted shear connectors in composite
structures are rarely used. One of the possible reasons could be the
lack of detailed research and design rules concerning their specific
Journal of Constructional Steel Research 88 (2013) 134–149
⁎ Corresponding author. Tel.: +381 641471748.
E-mail address: marko@imk.grf.bg.ac.rs (M. Pavlović).
0143-974X/$ – see front matter © 2013 Elsevier Ltd. All rights reserved.
http://dx.doi.org/10.1016/j.jcsr.2013.05.003
Contents lists available at SciVerse ScienceDirect
Journal of Constructional Steel Research