Contents lists available at ScienceDirect
Engineering Failure Analysis
journal homepage: www.elsevier.com/locate/engfailanal
Delayed catastrophe of a steel roofing structure of a shopping
facility
Janusz Krentowski
⁎
, Tadeusz Chyzy, Piotr Dunaj, Pawel Dunaj
Department of Geotechnics and Structural Mechanics, Faculty of Civil and Environmental Engineering, Bialystok University of Technology, Wiejska St.
45e, 15-351 Bialystok, Poland
ARTICLE INFO
Keywords:
Truss girder
Snow load
Bolted joints
Collapse
Reconstruction
ABSTRACT
The work describes the actions taken as a result of an unforeseen disaster of a shopping facility
that had been in operation for several decades. A considerable part of the facility's roof structure
unexpectedly collapsed under the impact of a snow layer, whose thickness did not exceed the
limit value specified in the current regulations. The roofing was made of steel segmental truss
girders (4 × 6 m) with a span of 24 m, joined together by bolts and welds. After securing the
facility against a possibility of further collapse, the extent of the damage was investigated. An
attempt was made to identify faults in the structural elements and in the connections made
several years earlier, as well as possible mistakes made during the modernization works several
months before the disaster. The actual strength parameters of the steel structural elements and
joints were determined. The effort of basic structural elements was analyzed, with particular
emphasis on the state of connections of successive segments of the damaged girders. The causes
of the disaster were determined. The work is concluded by presenting a concept and conditions
for lifting and reconstructing the damaged roof. It is worth highlighting that the roof was lifted as
a whole, without the need to disassemble purlins, steel sheets and insulation. The advantages and
disadvantages of different types of butt joints used in the construction were evaluated. Making
use of the results of the investigation, the recommendations concerning the design, construction
and operation of public facilities were formulated and relayed to participants of the investment
process.
1. Introduction
Modernization works of a building facility that has been operating for many years may add up to high risk of failure or a
construction disaster. Design work and subsequent renovation activities are infrequently preceded by detailed assessment of the
suitability of fundamental and secondary structural elements for the purpose of planned modifications.
Analyzing the published reports on building constructions that had undergone catastrophes, it was concluded that one of the most
important causes of disasters are mistakes in the load assessment affecting the construction, e.g.:
•
snow load [1–4],
•
wind load [5–7],
•
rainwater load [8],
https://doi.org/10.1016/j.engfailanal.2019.01.082
Received 8 November 2018; Received in revised form 26 January 2019; Accepted 28 January 2019
⁎
Corresponding author.
E-mail address: janusz@delta-av.com.pl (J. Krentowski).
Engineering Failure Analysis 98 (2019) 72–82
Available online 29 January 2019
1350-6307/ © 2019 Elsevier Ltd. All rights reserved.
T