Reliability Evaluation of Emergency Reponse Plan Design in
Buildings of Sriwijaya University 2019
evacuation time of 4,87 minutes. Through
evaluation of these variables, it’s concluded
that both buildings don’t have overall reliable
Emergency Response Plan (ERP) designs. This
study suggests that both buildings needs
improvements such as: providing standard
assembly points and proper signs, providing
adequate fire prevention and fire fighting
management, has written emergency
procedures and evacuation map which are
communicated to occupants, adding emergency
stairs and doors and to schedule routine
evacuation and fire drill.
Keywords: Emergency Response Plan
(ERP), fire management
Advances in Health Sciences Research, volume 25
2nd Sriwijaya International Conference of Public Health (SICPH 2019)
Copyright © 2020 The Authors. Published by Atlantis Press SARL.
This is an open access article distributed under the CC BY-NC 4.0 license -http://creativecommons.org/licenses/by-nc/4.0/. 86
Abstract - Sriwijaya University consists of
several different buildings for administration
and academic purpose to student
accommodations. A proper Emergency
Response Plan (ERP) is an important factor
in ensuring the safety of building occupants
from hazard such as fire, as it may reduce
evacuation time and prevent fatality and
injury. This study is a descriptive research
with qualitative approach. Samples were
selected through purposive sampling
techniques. Emergency Response Plan (ERP)
evaluation applied to Administration
Headquarters (KPA) and Sriwijaya University
Apartment Buildings in accordance with
NFPA 101 life safety code and SNI 03-1746-
2000. The evacuation time was calculated by
using SFPE 3rd Handbook of Fire Protection
Engineering 2002. This study shows that
Administration Headquarters met the standards
of emergency route, doors and stairs but
doesn’t have standard exit signs. Apartment
buildings met the standard for emergency
route, stairs and exit signs but not enough
emergency doors. Both buildings doesn’t have
written and standardized emergency
procedure and evacuation maps. Both
buildings don’t have standard assembly points.
With standard evacuation time of 2,5-3
minutes, Administration Headquarters has ideal
evacuation time of 1,96 minutes while
Apartment buildings has unsatisfying
Fatmalina Febry Anita Camelia
Occupational Health and Safety
Department
Faculty of Public Health
Sriwijaya University
Palembang, Indonesia
anita.camelia@gmail.com
Poppy Fujianti
Occupational Health and Safety
Department
Faculty of Public Health
Sriwijaya University
Palembang, Indonesia
poppyfujianti@gmail.com
Nutrition Department
Faculty of Public Health
Sriwijaya University
Palembang, Indonesia
Adji Randika
Occupational Health and Safety
Department
Faculty of Public Health
Sriwijaya University
Palembang, Indonesia
adjirandika1401@gmail.com
Nutrition Department
Faculty of Public Health
Sriwijaya University
Palembang, Indonesia
Adji Randika
Occupational Health and Safety
Department
Faculty of Public Health
Sriwijaya University
Palembang, Indonesia
adjirandika1401@gmail.com